Timeline

Project Development Schedule is as follows

The project Goal => first Gas in 2017

  • 2010-2011 Feasibility Studies
  • 2011-2012 Reconnaissance Surveys
  • 2012-2013 FEED Studies, Detailed surveys.
  • 2013-2015 Detailed Design, Equipment Trials
  • 2013-2015 Procurement of long lead items
  • 2015-2017 Installation